冷再生机施工进行碾压时的五点操作
来源:/ 日期:2022-10-24 发布人:
在做好冷再生施工的过程中能够节省很多的沥清、沙石等原料的应用,还能够节约工程项目的時间步骤。那么冷再生机施工进行碾压时的操作是怎样的呢?冷再生机租赁厂家为您讲解。
In the process of cold recycling construction, it can save a lot of raw materials such as asphalt, sand and gravel, and save the time and steps of the project. What is the operation of the cold recycling machine when rolling? The cold regeneration machine rental manufacturer will explain it to you.
(1)整形后,当混合料的含水量为佳含水量(+1%~+2%)时,应立刻用压路机在构造层全宽内停止碾压。直线和不设超高的平曲线段,由两侧路肩向路中心碾时,应堆叠1/2轮宽,后轮需超越两段的接缝处,后轮压完路面全宽时,即为一遍。普通需碾压4~6遍。
(1) After shaping, when the moisture content of the mixture is good (+1%~+2%), the roller shall be used to stop rolling within the full width of the structural layer immediately. For straight lines and flat curved sections without superelevation, when rolling from the shoulders on both sides to the center of the road, 1/2 wheel width shall be stacked. The rear wheel shall exceed the joint of the two sections. When the rear wheel has finished rolling the full width of the road, it is one time. Generally, it needs to be rolled 4~6 times.
(2)严禁压路机在已完成的或正在碾压的路段上调头或急刹车,应保证改进土层外表不受毁坏。
(2) It is strictly forbidden for the roller to turn around or brake suddenly on the completed or rolling road section, and the surface of the improved soil layer shall not be damaged.
(3)碾压过程中,水泥改进土的外表应一直坚持潮湿,如水分蒸发过快,应及时补撒少量的水,但严禁洒大水碾压。
(3) During rolling, the surface of cement improved soil shall always be wet. If the water evaporates too fast, a small amount of water shall be sprinkled in time, but it is strictly prohibited to sprinkle large amounts of water for rolling.
(4)经过拌和、整形的水泥改进土,宜在水泥初凝前并应在实验肯定的延迟时间内完成碾压,并到达请求的密实度,同时没有明显的轮迹。
(4) After mixing and shaping, the cement improved soil should be rolled before the initial setting of cement and within the delay time confirmed by the experiment to reach the required compactness without obvious wheel tracks.
(5)在碾压完毕之前,用平地机再终平一次,使其纵向顺适,路拱和高契合设计请求。终平应认真停止,需将部分高出局部刮除并扫出路外;关于部分低洼之处,不再停止找补,可留待下层施工时处置。
(5) Before the rolling is completed, the grader shall be used for final leveling again to make it smooth in the longitudinal direction, and the crown and height shall meet the design requirements. The final leveling shall be stopped carefully, and the part higher than the local level shall be scraped and swept away; Some low-lying areas will not be repaired and can be left for disposal during the construction of the lower layer.
This is the end of the five points of operation during the construction of the cold recycling machine. We remind you to do a good job of maintenance during the use of this machine, so as to avoid problems affecting the equipment quality and construction quality! For more information, please come to our website Consult!
下一篇:天气冷之前的冷再生机可以这样保养 上一篇:关于清扫机的惯例保护事项
阅读/ Recommended reading
- 冷再生机租赁:就地冷再生施质量控制要点 2024-09-21
- 冷再生机租赁:维特根冷再生机W 240 CR,用途广泛显神功 2024-09-15
- 冷再生机租赁:就地冷再生施工技术的原理及其特点分析 2024-09-04
- 冷再生机租赁——保养注意事项 2024-09-02
冷再生机租赁:路拌/冷再生机,让你的施工过程始终“开挂”
[2018-08-23]
作为路面施工装备中的一员 路拌/冷再生机一直以来均在路面解决方案里占有重要作用。而RS500路拌/冷再生机,作为一款性能出色的路面养护设备,更是行业里同类产品中的佼佼者。发动...